Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 04-30-2021 04-30-2021 --- Yes
Scoping (Agency Action) 06-01-2021 06-11-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 07-01-2022 09-02-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-24-2023 06-02-2023 07-21-2023 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 05-01-2023 08-21-2023 08-21-2023 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 04-30-2021 04-30-2021 --- Yes
Scoping (Agency Action) 06-01-2021 06-11-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 07-01-2022 09-02-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-24-2023 06-02-2023 07-21-2023 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 05-01-2023 08-21-2023 08-21-2023 No
In Progress
The project sponsor presented new project information last fall on October 13, 2022, to BOEM, NOAA, and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 21 WTGs for the project. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS. The project design changed the impacts analysis for consultations. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 04-30-2021 04-30-2021 --- Yes
Scoping (Agency Action) 06-01-2021 06-11-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 07-01-2022 09-02-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-24-2023 06-02-2023 07-21-2023 No
Issuance of Lead Agency Record of Decision (Agency Action) 05-01-2023 08-21-2023 08-21-2023 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 04-30-2021 04-30-2021 --- Yes
Scoping (Agency Action) 06-01-2021 06-11-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 07-01-2022 09-02-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-24-2023 06-02-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 05-01-2023 07-07-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 04-30-2021 04-30-2021 --- Yes
Scoping (Agency Action) 06-01-2021 06-11-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 07-01-2022 09-02-2022 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-24-2023 06-02-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 05-01-2023 07-07-2023 --- No