Permitting Action Modification History

Complete
This is a correction to the Dashboard - the ROD was executed two days early on July 3 (not on July 5 as was previously indicated). , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-30-2021 03-30-2021 --- Yes
Scoping (Agency Action) 04-29-2021 04-29-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 05-27-2022 06-24-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 02-17-2023 05-26-2023 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 03-31-2023 07-03-2023 --- Yes
Complete
ROD milestone completed early. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-30-2021 03-30-2021 --- Yes
Scoping (Agency Action) 04-29-2021 04-29-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 05-27-2022 06-24-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 02-17-2023 05-26-2023 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 03-31-2023 07-05-2023 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-30-2021 03-30-2021 --- Yes
Scoping (Agency Action) 04-29-2021 04-29-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 05-27-2022 06-24-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 02-17-2023 05-26-2023 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 03-31-2023 07-07-2023 --- No
In Progress
New Project information was submitted by the project sponsor on October 4, 2022, October 14, 2022, and October 27, 2022 in response to stakeholder concerns which included an updated COP and permit applications showing a shift to the location of the BL England substation to an adjacent portion of the same property which formerly housed elements of the BL England Generating Station and adjustment of the row A wind turbine generators (WTGs) as outlined in a joint letter signed by Ocean Wind LLC and Atlantic Shores Offshore Wind to create a distance of at least 1,500 meter between Ocean Wind 1’s and Atlantic Shores Offshore Wind South’s WTGs, and supplemental filing of information pertaining to maintenance dredging of the Barnegat Inlet Federal Navigation Project and upland material disposal and restoration of impacted submerged aquatic vegetation at a ratio of 3:1. The project sponsor’s delayed submission of their New Jersey Department of Environmental Protection (NJDEP) Land Resources Protection permit application will result in delayed issuance of NJDEP’s Coastal Zone Management Act (CZMA) federal consistency review decision. Delays to the Endangered Species Act (ESA) consultation with National Marine Fisheries Service of the National Oceanic and Atmospheric Administration (NOAA) and U.S. Fish and Wildlife Service (USFWS) and the Essential Fish Habitat (EFH) consultation with NOAA will result in delayed issuance of reasonable and prudent measures (with implementing terms and conditions) and conservation recommendations, respectively. BOEM requests this extension of the interim and final milestone dates to provide adequate time for BOEM to incorporate CZMA federal consistency conditions, as well as measures issued as a result of the ESA and EFH consultations and developed through the Section 106 review, into the final EIS and ROD. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-30-2021 03-30-2021 --- Yes
Scoping (Agency Action) 04-29-2021 04-29-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 05-27-2022 06-24-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 02-17-2023 05-26-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 03-31-2023 07-07-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-30-2021 03-30-2021 --- Yes
Scoping (Agency Action) 04-29-2021 04-29-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 05-27-2022 06-24-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 02-17-2023 03-03-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 03-31-2023 04-14-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-30-2021 03-30-2021 --- Yes
Scoping (Agency Action) 04-29-2021 04-29-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 05-27-2022 06-24-2022 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 02-17-2023 03-03-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 03-31-2023 04-14-2023 --- No