Permitting Action Modification History
Modifications on 09/12/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 11-05-2015 | 11-05-2015 | --- | Yes |
| Scoping (Agency Action) | 11-05-2015 | 11-05-2015 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 09-27-2016 | 09-27-2016 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 06-29-2017 | 06-29-2017 | --- | Yes |
| Issuance of Lead Agency Record of Decision (Agency Action) | 10-13-2017 | 10-13-2017 | --- | Yes |