USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2015 11-30-2015 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 11-22-2017 12-22-2017 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-21-2017 12-22-2017 --- Yes