Permitting Action Modification History
Modifications on 09/12/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 11-09-2015 | 11-09-2015 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 06-30-2017 | 06-30-2017 | --- | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 12-29-2017 | 12-15-2017 | --- | Yes |