Permitting Action Modification History

Complete
The final EFH milestone was completed ahead of schedule.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2019 06-10-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 04-01-2021 08-10-2022 --- Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 04-30-2021 11-28-2022 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2019 06-10-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 04-01-2021 08-10-2022 --- Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 04-30-2021 01-15-2023 --- No
Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2019 06-10-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 04-01-2021 08-10-2022 --- Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 04-30-2021 01-15-2023 --- No
Planned
Original Target Date Data Entry Effort , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2019 06-10-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 04-01-2021 08-10-2022 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 04-30-2021 01-15-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 06-10-2022 06-10-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 08-10-2022 08-10-2022 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-15-2023 01-15-2023 --- No