Permitting Action Modification History

Complete
Completed one month early.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-26-2021 06-10-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2021 08-10-2022 --- Yes
ESA Consultation Concludes (Agency Action) 04-01-2022 12-12-2022 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-26-2021 06-10-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2021 08-10-2022 --- Yes
ESA Consultation Concludes (Agency Action) 04-01-2022 01-15-2023 --- No
Complete
Per email from Michael Barnett at NMFS and after Scott Kelly's discussion with Regional Admin (Andy Strehlcheck) and Joe's meeting with Helen.  Marking complete per NOAA/NMFS direction.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-26-2021 06-10-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2021 08-10-2022 --- Yes
ESA Consultation Concludes (Agency Action) 04-01-2022 01-15-2023 --- No
Planned
Original Target Date Data Entry Effort , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-26-2021 06-10-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2021 08-10-2022 --- No
ESA Consultation Concludes (Agency Action) 04-01-2022 01-15-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-10-2022 06-10-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 08-10-2022 08-10-2022 --- No
ESA Consultation Concludes (Agency Action) 01-15-2023 01-15-2023 --- No