Permitting Action Modification History

Complete
FWS delivered the project Biological and Conference opinion to the Corp on 1/13/23, 10 days early. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 09-13-2021 06-10-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2021 08-10-2022 --- Yes
ESA Consultation Concludes (Agency Action) 04-01-2022 01-13-2023 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 09-13-2021 06-10-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2021 08-10-2022 --- Yes
ESA Consultation Concludes (Agency Action) 04-01-2022 01-23-2023 --- No
Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 09-13-2021 06-10-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2021 08-10-2022 --- Yes
ESA Consultation Concludes (Agency Action) 04-01-2022 01-23-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-10-2022 06-10-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-10-2022 08-10-2022 --- No
ESA Consultation Concludes (Agency Action) 01-23-2023 01-23-2023 --- No