Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-08-2019 07-08-2019 --- Yes
Completeness Determination (Agency Action) 01-06-2022 01-06-2022 --- Yes
Complete application submitted (Applicant Action) 02-10-2023 02-27-2023 --- Yes
Issuance of Decision (Agency Action) 05-17-2023 07-17-2024 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-08-2019 07-08-2019 --- Yes
Completeness Determination (Agency Action) 01-06-2022 01-06-2022 --- Yes
Complete application submitted (Applicant Action) 02-10-2023 02-27-2023 --- Yes
Issuance of Decision (Agency Action) 05-17-2023 07-17-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-08-2019 07-08-2019 --- Yes
Completeness Determination (Agency Action) 01-06-2022 01-06-2022 --- Yes
Complete application submitted (Applicant Action) 02-10-2023 02-28-2023 --- No
Issuance of Decision (Agency Action) 05-17-2023 07-17-2024 --- No
In Progress
The primary driver of the schedule change, as described in the attached memo, is a requirement for the applicant's contractor to recollect and test 3 additional sediment samples, as the original samples exceeded the holding times specified in the Corps/EPA/Approved sediment analysis plan and the Corps/EPAs 2003 Regional Implementation Agreement and cannot be considered scientifically sound. The memo also describes an additional risk to schedule associated with proposed sediment deposition sites behind Corps Levees parallel to the federal navigation channel. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-08-2019 07-08-2019 --- Yes
Completeness Determination (Agency Action) 01-06-2022 01-06-2022 --- Yes
Complete application submitted (Applicant Action) 02-10-2023 02-10-2023 --- No
Issuance of Decision (Agency Action) 05-17-2023 07-17-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-08-2019 07-08-2019 --- Yes
Completeness Determination (Agency Action) 01-06-2022 01-06-2022 --- Yes
Issuance of Decision (Agency Action) 05-17-2023 05-17-2023 --- No