Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 01-07-2019 01-07-2019 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 06-05-2019 06-05-2019 --- Yes
Publication of Public Notice (Agency Action) 08-01-2019 08-01-2019 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 08-20-2021 07-17-2024 --- Yes
In Progress
The primary driver of the schedule change, as described in the attached memo, is a requirement for the applicant's contractor to recollect and test 3 additional sediment samples, as the original samples exceeded the holding times specified in the Corps/EPA/Approved sediment analysis plan and the Corps/EPAs 2003 Regional Implementation Agreement and cannot be considered scientifically sound. The memo also describes an additional risk to schedule associated with proposed sediment deposition sites behind Corps Levees parallel to the federal navigation channel. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 01-07-2019 01-07-2019 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 06-05-2019 06-05-2019 --- Yes
Publication of Public Notice (Agency Action) 08-01-2019 08-01-2019 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 08-20-2021 07-17-2024 --- No