Permitting Action Modification History
Modifications on 02/28/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 01-08-2021 | 01-08-2021 | --- | Yes |
| NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) | 02-08-2021 | 02-08-2021 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 07-08-2021 | 10-01-2021 | --- | Yes |