Permitting Action Modification History

Complete
Completed milestone ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 10-21-2016 10-21-2016 --- Yes
Section 106 consultation concluded (Agency Action) 07-23-2021 12-19-2022 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 10-21-2016 10-21-2016 --- Yes
Section 106 consultation concluded (Agency Action) 07-23-2021 12-23-2022 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 10-21-2016 10-21-2016 --- Yes
Section 106 consultation concluded (Agency Action) 07-23-2021 09-22-2022 --- No