Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 12-09-2020 12-09-2020 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-23-2020 12-23-2020 --- Yes
Publication of Public Notice (Agency Action) 01-08-2021 01-06-2021 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 01-18-2022 01-18-2022 --- Yes