Permitting Action Modification History
Modifications on 10/25/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 05-03-2019 | 05-03-2019 | --- | Yes |
| Scoping (Agency Action) | 06-03-2019 | 06-03-2019 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 03-06-2020 | 05-14-2021 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 02-12-2021 | 03-25-2022 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 05-13-2021 | 04-29-2022 | --- | No |