Permitting Action Modification History
Modifications on 06/16/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 09-19-2019 | 09-19-2019 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 09-19-2019 | 09-19-2019 | --- | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 02-06-2020 | 11-20-2019 | --- | Yes |