USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
Idaho Power provide a complete application package ahead of schedule and USACE processed the permit within their stipulated time frame.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-01-2022 01-30-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-15-2022 12-12-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-30-2022 03-20-2024 --- Yes
In Progress
Proponent submitted final documents for permit
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-01-2022 01-30-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-15-2022 12-12-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-30-2022 06-28-2024 --- No
Planned
After review, applicant was missing maps
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-01-2022 01-30-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-15-2022 12-31-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-30-2022 06-28-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-01-2022 01-30-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-15-2022 11-20-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-30-2022 06-28-2024 --- No
Planned
Project sponsor has not provided USACE with all required information to complete processing of permit. The project crosses through U.S. Army Corps of Engineers Portland District and Walla Walla District Regulatory boundaries. The Portland District is the lead district for evaluation of the Department of the Army permit requirements. The Portland District received a permit application for the proposed project on 30 January 2023 and found the application to be incomplete by 3 February 2023. Upon coordination with BLM and the applicant, a revised application will be submitted for the proposed project on or by 31 December 2023. The updated permit review schedule is as follows: Application/Preconstruction Notification (PCN) submitted: 30 January 2023 Complete PCN : 31 December 2023 Public Notice published (if PCN complete): N/A Final verification/permit decision rendered: 28 June 2024 The delay in receipt of a complete PCN and the requirement for an individual 401 water quality certification from the state of Oregon shifts the subsequent milestones, resulting in a final permit decision six months after the currently published date of 15 February 2024. No public notice is anticipated at this time since there are no proposed impacts that exceed the thresholds of the Nationwide Permit 57, which authorizes certain activities under Section 404 of the Clean Water Act for electric utility line and telecommunications activities.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-01-2022 01-30-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-15-2022 12-31-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-30-2022 06-28-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-01-2022 01-31-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-15-2022 02-15-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-30-2022 05-31-2023 --- No
Planned
Project proponent has not submitted an application; upon coordination with the project proponent, the application will not be submitted until January 31, 2023. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-01-2022 01-31-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-15-2022 02-15-2023 --- No
Publication of Public Notice (Agency Action) 04-15-2022 02-15-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-30-2022 05-31-2023 --- No
Planned
Original Target Date Data Entry Effort
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-01-2022 08-01-2022 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-15-2022 08-15-2022 --- No
Publication of Public Notice (Agency Action) 04-15-2022 08-15-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-30-2022 02-15-2023 --- No