Permitting Action Modification History
Modifications on 02/25/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-20-2019 | 06-20-2019 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 06-20-2019 | 06-20-2019 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 11-01-2019 | 07-29-2019 | --- | Yes |