Permitting Action Modification History

Complete
Updated a milestone that was not previously identified for this project.  The system wouldn't let me move forward without putting something in there.  Also updated the date for the last milestone.  This was completed ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-13-2017 01-13-2017 --- Yes
Completeness Determination (Agency Action) 12-19-2019 08-10-2021 --- Yes
Complete application submitted (Applicant Action) 12-19-2019 08-10-2021 --- Yes
Issuance of Decision (Agency Action) 10-31-2022 12-19-2022 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-13-2017 01-13-2017 --- Yes
Completeness Determination (Agency Action) 12-19-2019 08-10-2021 --- Yes
Issuance of Decision (Agency Action) 10-31-2022 12-23-2022 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-13-2017 01-13-2017 --- Yes
Completeness Determination (Agency Action) 12-19-2019 08-10-2021 --- Yes
Issuance of Decision (Agency Action) 10-31-2022 09-22-2022 --- No