Modifications on 02/28/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 07-10-2018 | 07-10-2018 | --- | Yes |
| NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) | 10-24-2018 | 10-24-2018 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 06-10-2019 | 02-08-2019 | --- | Yes |