Permitting Action Modification History
Modifications on 02/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| EFH Consultation Request Submitted – EFH Assessment (Agency Action) | 03-27-2028 | 03-27-2028 | --- | No |
| NOAA determines EFH Assessment is Complete (Agency Action) | 08-29-2028 | 08-29-2028 | --- | No |
| NOAA Issues any EFH Conservation Recommendations (Agency Action) | 11-27-2028 | 11-27-2028 | --- | No |
Modifications on 08/19/2024
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| EFH Consultation Request Submitted – EFH Assessment (Agency Action) | --- | --- | --- | No |
| NOAA determines EFH Assessment is Complete (Agency Action) | --- | --- | --- | No |
| NOAA Issues any EFH Conservation Recommendations (Agency Action) | --- | --- | --- | No |