Permitting Action Modification History
Modifications on 05/30/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 11-16-2016 | 11-16-2016 | --- | Yes |
| NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) | 11-16-2016 | 11-16-2016 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 02-28-2017 | 02-28-2017 | --- | Yes |