USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 05-16-2028 05-16-2028 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 06-15-2028 06-15-2028 --- No
Publication of Public Notice (Agency Action) 06-30-2028 06-30-2028 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-17-2029 09-17-2029 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) --- --- --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) --- --- --- No
Publication of Public Notice (Agency Action) --- --- --- No
Final Verification/Permit Decision Rendered (Agency Action) --- --- --- No