Permitting Action Modification History
Modifications on 11/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 02-15-2028 | 02-15-2028 | --- | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 03-16-2028 | 03-16-2028 | --- | No |
| ESA Consultation Concludes (Agency Action) | 07-31-2028 | 07-31-2028 | --- | No |