Permitting Action Modification History
Modifications on 10/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 01-15-2027 | 01-15-2027 | --- | No |
| Scoping (Agency Action) | 01-15-2027 | 01-15-2027 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 12-01-2028 | 12-01-2028 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 01-09-2029 | 01-09-2029 | --- | No |