Permitting Action Modification History
Modifications on 10/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 08-17-2026 | 08-17-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 09-17-2026 | 09-17-2026 | --- | Yes |
| Publication of Public Notice (Agency Action) | 01-15-2027 | 01-15-2027 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 01-09-2029 | 01-09-2029 | --- | No |