Permitting Action Modification History

Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-05-2027 03-05-2027 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 04-05-2027 04-05-2027 --- No
ESA Consultation Concludes (Agency Action) 07-19-2027 07-19-2027 --- No