Permitting Action Modification History
Modifications on 09/28/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 07-11-2028 | 07-11-2028 | --- | No |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 08-10-2028 | 08-10-2028 | --- | No |
| Publication of Public Notice (Agency Action) | 08-25-2028 | 08-25-2028 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 09-28-2029 | 09-28-2029 | --- | No |