Permitting Action Modification History
Modifications on 09/28/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Submittal of draft initial Plan of Operations (Applicant Action) | 03-31-2027 | 03-31-2027 | --- | No |
| Submittal of complete initial Plan of Operations (Applicant Action) | 07-29-2027 | 07-29-2027 | --- | No |
| Acceptance of complete initial Plan of Operations (Agency Action) | 08-27-2027 | 08-27-2027 | --- | No |
| Submittal of final Plan of Operations and financial assurance (Applicant Action) | 01-25-2030 | 01-25-2030 | --- | No |
| Approval of final Plan of Operations (Agency Action) | 04-26-2030 | 04-26-2030 | --- | No |