Permitting Action Modification History

In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 11-14-2023 11-14-2023 --- Yes
Completeness determination for Mine Plan of Operations (Agency Action) 06-10-2024 06-10-2024 --- Yes
Revised Mine Plan of Operations received (Applicant Action) --- --- --- No
Issuance of decision for Mine Plan of Operations (Agency Action) 12-17-2027 12-17-2027 --- No
Financial assurance received (Applicant Action) 12-17-2027 12-17-2027 --- No