Permitting Action Modification History

Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-25-2026 09-25-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 11-24-2026 11-24-2026 --- No
Publication of Public Notice (Agency Action) 12-09-2026 12-09-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 01-14-2028 01-14-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-25-2026 09-25-2026 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 11-24-2026 11-24-2026 --- No
Publication of Public Notice (Agency Action) 12-09-2026 12-09-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 01-14-2028 01-14-2028 --- No