USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 01-15-2027 01-15-2027 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 03-17-2027 03-17-2027 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 05-19-2027 05-19-2027 --- No