Permitting Action Modification History
Modifications on 08/31/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 02-15-2027 | 02-15-2027 | --- | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 03-15-2027 | 03-15-2027 | --- | No |
| ESA Consultation Concludes (Agency Action) | 07-28-2027 | 07-28-2027 | --- | No |