Permitting Action Modification History
Modifications on 09/03/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 09-04-2026 | 09-02-2026 | --- | Yes |
| Scoping (Agency Action) | 10-19-2026 | 10-19-2026 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 04-28-2028 | 04-28-2028 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 05-05-2028 | 05-05-2028 | --- | No |
Modifications on 08/31/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 09-04-2026 | 09-04-2026 | --- | No |
| Scoping (Agency Action) | 10-19-2026 | 10-19-2026 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 04-28-2028 | 04-28-2028 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 05-05-2028 | 05-05-2028 | --- | No |