Permitting Action Modification History
Modifications on 09/14/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 07-28-2026 | 07-28-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-28-2026 | 07-28-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 10-01-2026 | 09-11-2026 | --- | Yes |
Modifications on 09/14/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 07-28-2026 | 07-28-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-28-2026 | 07-28-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 10-01-2026 | 09-11-2026 | --- | Yes |
Modifications on 08/10/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 07-28-2026 | 07-28-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-28-2026 | 07-28-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 10-01-2026 | 10-01-2026 | --- | No |