Permitting Action Modification History

Complete
Agency was able to gain SHPO concurrence early and consulation is now complete., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-28-2026 08-27-2026 --- Yes
Section 106 consultation concluded (Agency Action) 10-01-2026 09-24-2026 --- Yes
In Progress
Corps initiated Section 106 consultation and provided effect determination early. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-28-2026 08-27-2026 --- Yes
Section 106 consultation concluded (Agency Action) 10-01-2026 10-01-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-28-2026 08-28-2026 --- No
Section 106 consultation concluded (Agency Action) 10-01-2026 10-01-2026 --- No