Permitting Action Modification History
Modifications on 08/05/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 05-26-2026 | 05-22-2026 | Yes |
| Section 106 consultation concluded (Agency Action) | 07-22-2026 | 07-29-2026 | Yes |
Modifications on 07/31/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | --- | 05-26-2026 | Yes |
| Section 106 consultation concluded (Agency Action) | --- | 07-22-2026 | Yes |