Permitting Action Modification History

Complete
FWS consultation was completed early - this was an extension of an existing mining operation and there was already a lot of information existing which helped expedite the review., basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-23-2026 07-23-2026 Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 08-24-2026 08-24-2026 Yes
ESA Consultation Concludes (Agency Action) 09-21-2026 08-26-2026 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-23-2026 07-23-2026 Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 08-24-2026 08-24-2026 Yes
ESA Consultation Concludes (Agency Action) 09-21-2026 09-21-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-23-2026 07-23-2026 Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 08-24-2026 08-24-2026 No
ESA Consultation Concludes (Agency Action) 09-21-2026 09-21-2026 No