Permitting Action Modification History
Modifications on 09/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 04-20-2026 | 04-20-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 05-19-2026 | 05-19-2026 | --- | Yes |
| Publication of Public Notice (Agency Action) | 09-18-2026 | 09-18-2026 | --- | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 09-15-2028 | 09-15-2028 | --- | No |
Modifications on 07/13/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 04-20-2026 | 04-20-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 05-19-2026 | 05-19-2026 | --- | Yes |
| Publication of Public Notice (Agency Action) | 09-18-2026 | 09-18-2026 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 09-15-2028 | 09-15-2028 | --- | No |