Permitting Action Modification History
Modifications on 09/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 09-18-2026 | 09-18-2026 | --- | Yes |
| Scoping (Agency Action) | 09-18-2026 | 09-18-2026 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 08-11-2028 | 08-11-2028 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 09-15-2028 | 09-15-2028 | --- | No |
Modifications on 07/17/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 09-18-2026 | 09-18-2026 | --- | No |
| Scoping (Agency Action) | 09-18-2026 | 09-18-2026 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 08-11-2028 | 08-11-2028 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 09-15-2028 | 09-15-2028 | --- | No |
Modifications on 07/13/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 09-18-2026 | 09-18-2026 | --- | No |
| Scoping (Agency Action) | --- | --- | --- | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | --- | --- | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | --- | --- | --- | No |
| Official Notice of Availability of a Supplemental Draft EIS published in the FR (Agency Action) | --- | --- | --- | No |
| Official Notice of Availability of a Supplemental Final EIS published in the FR (Agency Action) | 08-11-2028 | 08-11-2028 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 09-15-2028 | 09-15-2028 | --- | No |