Permitting Action Modification History

In Progress
The PSD construction permit application dated August 31, 2026 was received on September 1, 2026.  Additional requested information was received on October 9, 2026 and October 12, 2026, and TDEC deemed the application complete on November 2, 2026., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-31-2026 08-31-2026 --- Yes
Application deemed complete (Agency Action) 09-28-2026 11-02-2026 --- Yes
Final decision/agency action (Agency Action) 04-08-2027 04-08-2027 --- No
Planned
The project sponsor broke the permit application into two parts. Part one was provided as the initial application and part two is yet to be submitted.  The additional information from part two is required in order for State to deem the application complete., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-31-2026 08-31-2026 --- Yes
Application deemed complete (Agency Action) 09-28-2026 11-16-2026 --- No
Final decision/agency action (Agency Action) 04-08-2027 04-08-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-31-2026 08-31-2026 --- Yes
Application deemed complete (Agency Action) 09-28-2026 09-28-2026 --- No
Final decision/agency action (Agency Action) 04-08-2027 04-08-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-31-2026 08-31-2026 --- No
Application deemed complete (Agency Action) 09-28-2026 09-28-2026 --- No
Final decision/agency action (Agency Action) 04-08-2027 04-08-2027 --- No