Permitting Action Modification History

In Progress
U.S. Army Corps of Engineers (USACE) Nashville District reviewed the application for the Real Estate consent submitted by the project sponsor on 30 September 2026, and determined it to be complete on 20 October 2026 (ahead of the original target date of 24 October 2026)., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 10-01-2026 09-30-2026 --- Yes
Completed application received (Applicant Action) 10-24-2026 10-20-2026 --- Yes
Issuance of decision for permit/approval (Agency Action 01-22-2027 01-22-2027 --- No
In Progress
The project sponsor submitted initial application one day ahead of 10/1/26 target date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 10-01-2026 09-30-2026 --- Yes
Completed application received (Applicant Action) 10-24-2026 10-24-2026 --- No
Issuance of decision for permit/approval (Agency Action 01-22-2027 01-22-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 10-01-2026 10-01-2026 --- No
Completed application received (Applicant Action) 10-24-2026 10-24-2026 --- No
Issuance of decision for permit/approval (Agency Action 01-22-2027 01-22-2027 --- No