Permitting Action Modification History

In Progress
U.S. Army Corps of Engineers (USACE) Nashville District reviewed the Section 408 request submitted by the project sponsor on 30 September 30 2026, and determined it to be a complete request on 16 October 2026 (ahead of the original target date of 01 November 2026)., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-01-2026 09-30-2026 --- Yes
Completeness Determination (Agency Action) 11-01-2026 10-16-2026 --- Yes
Issuance of Decision (Agency Action) 12-30-2026 12-30-2026 --- No
Planned
The project sponsor submitted initial application one day ahead of 10/1/26 target date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-01-2026 09-30-2026 --- Yes
Completeness Determination (Agency Action) 11-01-2026 11-01-2026 --- No
Issuance of Decision (Agency Action) 12-30-2026 12-30-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-01-2026 10-01-2026 --- No
Completeness Determination (Agency Action) 11-01-2026 11-01-2026 --- No
Issuance of Decision (Agency Action) 12-30-2026 12-30-2026 --- No