Permitting Action Modification History
Modifications on 08/10/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 07-24-2026 | 07-24-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Informal (Agency Action) | 08-12-2026 | 08-07-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 09-01-2026 | 08-07-2026 | --- | Yes |
Modifications on 07/24/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 07-24-2026 | 07-24-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Informal (Agency Action) | 08-12-2026 | 08-12-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 09-01-2026 | 09-01-2026 | --- | No |
Modifications on 06/17/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 07-24-2026 | 07-24-2026 | --- | No |
| FWS determines ESA Consultation Package is Complete - Informal (Agency Action) | 08-12-2026 | 08-12-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 09-01-2026 | 09-01-2026 | --- | No |