Permitting Action Modification History
Modifications on 09/01/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 06-12-2026 | 06-12-2026 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 09-01-2026 | 09-01-2026 | --- | Yes |
Modifications on 06/17/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 06-12-2026 | 06-12-2026 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 09-01-2026 | 09-01-2026 | --- | No |