Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 03-26-2026 03-26-2026 --- Yes
Issuance of a Final EA (Agency Action) 09-11-2026 09-11-2026 --- Yes
EA Process Concluded (Agency Action) 09-11-2026 09-11-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 03-26-2026 03-26-2026 --- Yes
Issuance of a Final EA (Agency Action) 09-11-2026 09-11-2026 --- No
EA Process Concluded (Agency Action) 09-11-2026 09-11-2026 --- No