Permitting Action Modification History

Complete
Early submission of consultation package resulted in an earlier review by USFWS. USFWS completed review ahead of their original target date., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-14-2026 08-25-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-13-2026 09-02-2026 --- Yes
ESA Consultation Concludes (Agency Action) 03-26-2027 09-02-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-14-2026 08-25-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-13-2026 09-24-2026 --- No
ESA Consultation Concludes (Agency Action) 03-26-2027 02-06-2027 --- No
Planned
The Section 404 Complete Application was received ahead of schedule from the Project Sponsor. This facilitated a positive ripple effect, accelerating progress toward subsequent project milestones including starting the EA, ESA, and Section 106., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-14-2026 08-25-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-13-2026 09-24-2026 --- No
ESA Consultation Concludes (Agency Action) 03-26-2027 02-06-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-14-2026 10-14-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-13-2026 11-13-2026 --- No
ESA Consultation Concludes (Agency Action) 03-26-2027 03-26-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-14-2026 10-14-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-13-2026 11-13-2026 --- No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) --- --- --- No
ESA Consultation Concludes (Agency Action) 03-26-2027 03-26-2027 --- No