Permitting Action Modification History

In Progress
The Section 404 Complete Application was received ahead of schedule by the Project Sponsor., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-15-2026 06-12-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-30-2026 06-12-2026 --- Yes
Publication of Public Notice (Agency Action) 08-14-2026 06-26-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 08-13-2027 06-25-2027 --- No
Planned
Applicant submitted application ahead of schedule., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-15-2026 06-12-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-30-2026 07-12-2026 --- No
Publication of Public Notice (Agency Action) 08-14-2026 08-14-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-13-2027 08-13-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-15-2026 06-15-2026 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-30-2026 07-30-2026 --- No
Publication of Public Notice (Agency Action) 08-14-2026 08-14-2026 --- No
Provisional Notification (Agency Action) --- --- --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-13-2027 08-13-2027 --- No