Permitting Action Modification History
Modifications on 08/14/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 06-11-2026 | 06-09-2026 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 09-09-2026 | 08-13-2026 | --- | Yes |
Modifications on 06/10/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 06-11-2026 | 06-09-2026 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 09-09-2026 | 09-09-2026 | --- | No |
Modifications on 05/29/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 06-11-2026 | 06-11-2026 | --- | No |
| Section 106 consultation concluded (Agency Action) | 09-09-2026 | 09-09-2026 | --- | No |