Permitting Action Modification History
Modifications on 07/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-11-2026 | 06-09-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-10-2026 | 07-02-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 11-23-2026 | 07-02-2026 | --- | Yes |
Modifications on 06/10/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-11-2026 | 06-09-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-10-2026 | 07-10-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 11-23-2026 | 11-23-2026 | --- | No |
Modifications on 05/29/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-11-2026 | 06-11-2026 | --- | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-10-2026 | 07-10-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 11-23-2026 | 11-23-2026 | --- | No |