Permitting Action Modification History
Modifications on 05/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Submittal of draft initial Plan of Operations (Applicant Action) | 03-20-2026 | 03-20-2026 | --- | Yes |
| Submittal of complete initial Plan of Operations (Applicant Action) | 07-16-2026 | 07-16-2026 | --- | No |
| Acceptance of complete initial Plan of Operations (Agency Action) | 07-29-2026 | 07-29-2026 | --- | No |
| Submittal of final Plan of Operations and financial assurance (Applicant Action) | 03-06-2028 | 03-06-2028 | --- | No |
| Approval of final Plan of Operations (Agency Action) | 03-20-2028 | 03-20-2028 | --- | No |
Modifications on 05/19/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Submittal of draft initial Plan of Operations (Applicant Action) | 03-20-2026 | 03-20-2026 | --- | No |
| Submittal of complete initial Plan of Operations (Applicant Action) | 07-16-2026 | 07-16-2026 | --- | No |
| Acceptance of complete initial Plan of Operations (Agency Action) | 07-29-2026 | 07-29-2026 | --- | No |
| Submittal of final Plan of Operations and financial assurance (Applicant Action) | 03-06-2028 | 03-06-2028 | --- | No |
| Approval of final Plan of Operations (Agency Action) | 03-20-2028 | 03-20-2028 | --- | No |