Permitting Action Modification History

In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Submittal of draft initial Plan of Operations (Applicant Action) 03-20-2026 03-20-2026 --- Yes
Submittal of complete initial Plan of Operations (Applicant Action) 07-16-2026 07-16-2026 --- Yes
Acceptance of complete initial Plan of Operations (Agency Action) 07-29-2026 07-29-2026 --- Yes
Submittal of final Plan of Operations and financial assurance (Applicant Action) 03-06-2028 03-06-2028 --- No
Approval of final Plan of Operations (Agency Action) 03-20-2028 03-20-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Submittal of draft initial Plan of Operations (Applicant Action) 03-20-2026 03-20-2026 --- Yes
Submittal of complete initial Plan of Operations (Applicant Action) 07-16-2026 07-16-2026 --- Yes
Acceptance of complete initial Plan of Operations (Agency Action) 07-29-2026 07-29-2026 --- No
Submittal of final Plan of Operations and financial assurance (Applicant Action) 03-06-2028 03-06-2028 --- No
Approval of final Plan of Operations (Agency Action) 03-20-2028 03-20-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Submittal of draft initial Plan of Operations (Applicant Action) 03-20-2026 03-20-2026 --- Yes
Submittal of complete initial Plan of Operations (Applicant Action) 07-16-2026 07-16-2026 --- No
Acceptance of complete initial Plan of Operations (Agency Action) 07-29-2026 07-29-2026 --- No
Submittal of final Plan of Operations and financial assurance (Applicant Action) 03-06-2028 03-06-2028 --- No
Approval of final Plan of Operations (Agency Action) 03-20-2028 03-20-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Submittal of draft initial Plan of Operations (Applicant Action) 03-20-2026 03-20-2026 --- No
Submittal of complete initial Plan of Operations (Applicant Action) 07-16-2026 07-16-2026 --- No
Acceptance of complete initial Plan of Operations (Agency Action) 07-29-2026 07-29-2026 --- No
Submittal of final Plan of Operations and financial assurance (Applicant Action) 03-06-2028 03-06-2028 --- No
Approval of final Plan of Operations (Agency Action) 03-20-2028 03-20-2028 --- No